Vitória Airport: food court and kiosks
Mobile hoarding, demolition of granite flooring for ramps and pipework, and laying of quartzite flooring supplied by the client. Electrical and plumbing installations with design and ART registration, distribution boards for the kiosks, and a drywall office with ceiling, painting and flooring.
- Client
- Cafeteria e Choperia do Mestre
- Location
- Aeroporto, Vitória
- Dates
- May 2018 - Jun 2018
- Intervention area
- 210 m²
- Status
- Completed
Quantities and quality control
| Item | Unit | Quantity |
|---|---|---|
| Avohai quartzite flooring t=3 cm, installation (flooring supplied by client) | m² | 195 |
| Floor grouting | m² | 195 |
| General site cleaning and hoarding removal (site area) | m² | 210 |
| Movable plywood site hoarding h=2.20 m | m | 76 |
| Demolition of existing granite flooring, including screed (contract) | m² | 22 |
| Demolition of existing granite flooring (1st change order, miscellaneous works) | m² | 15.54 |
| Electrical points installed (124 planned + 93 added) | pontos | 217 |
| Copper cable 1000 V, 50 mm² | m | 400 |
Source: the project's progress reports.